1 |
5977 |
02/01/2012 |
C3/10956/2010 |
M/S.MUKTHA FOUNDATIONS PVT. LTD, REP BY ITS DIRECTOR HITESH G.SHAH No.77/8, 4th Main Road, 5th Block, Anna Nagar, Chennai-40 |
S.No.739/1A, 1B, 2B, 3B (Asper Patta) S.No.739/1A, 1B, 2, 3 (Asper Document) of Poonamallee Village, Trunk Road, Chennai. |
Poonamallee |
Basement Floor + Stilt Floor + First Floor to 10th Floor including service floor Commercial Building. |
2692.68 |
|
|
|
|
|
|
|
2 |
5978 |
03/01/2012 |
C3/12448/2010 |
M/S.A.R.PROPERTY DEVELOPERS PVT. LTD., F-72, East Anna Nagar, Chennai-102. & M/S.A.I.ENTERPRISES PVT. LTD., F-41A, East Anna Nagar, Chennai-102 |
S.No.58/1B, 58/2A2, 58/2A1B of Maduravoyal Village, Poonamallee High Road (N.H.4) Chennai. |
Maduravoyal |
Construction of Block-A Hotel Building with double Basement Floors + Ground Floor + 14 Floors (164 Guest Rooms) and Block-B Residential Building with Basement Floor + Stilt Floor cum Ground Floor + 4 Floors (180 Dwelling Units) |
7935.66 |
|
|
|
|
|
|
|
3 |
5979 |
03/01/2012 |
C3/11554/2011 |
R.RAVEENDRAN, No.8, 4th Floor, North Boag Road, T.Nagar, Chennai-17 |
R.S.No.1798/1, 1798/25 & 1798/27, Block No.28 of Tondiarpet, Door No.7 & 8, Thiruvotriyur High Road, Old Washermenpet, Chennai |
Tondiarpet |
Renewal of PP Construction of Triple Basement Floor + 6 Floors Commercial Building for Party Hall Show Rooms and 6Nos. Theaters. |
|
|
|
|
|
|
|
|
4 |
5981 |
05/01/2012 |
C3/17084/2010 |
C.SHANKAR (POA) POA FOR SHAHUL HAMEED & BROTHER, No.216/65, Alwarpet Street, Alwarpet, Chennai-18 |
S.No.267/2B, 3B, 5, 6, 7, 8, 9 & 10, MMRD Road, Zamin Pallavaram Village, Chennai. |
Zamin Pallavaram |
Construction of Common Basement Floor + Common Stilt Floor + First Floor + 2nd Floor to 15th Floors (2Blocks) Connection at 14th & 15th Floor Level. |
|
|
|
|
Multi-storeyed Building comprising Common Basement Floor + Common Stilt Floor + 1st Floor + 2nd Floor to 15 Floors (2 Blocks) connection at 14th & 15th Floor level of Residential Building with 207 Dwelling Units |
EC/S-I/8808/2015 |
EC/South-I/383/2015 dated 04-09-2015 |
|
5 |
5982 |
06/01/2012 |
C3/8889/2010 |
M/S.ANAND CITY CENTER HOLDINGS PVT. LTD., No.10 & 11, Chennai City Center, Dr.Radhakrishnan Salai, Mylapore, Chennai-4 |
Anna Salai, Chennai in R.S.No.35/32, 35/33, 35/34, 35/79, 35/85, 35/143, 35/148, Block No.6, Nungambakkam Village. |
Nungambakkam |
Revised PP for the Proposed construction of Two Basement Floor + Stilt Part + Ground Floor Part + 11 Floors for the Office and Hotel proposal. |
6498.82 |
|
|
|
Multi-storeyed Building comprising Double Basement Floor + Stilt Floor (Part) + Ground Floor (Part) + 11 Floors for the Office and Hotel purpose |
EC/CCW/N&C/ 11600/2009 |
EC/Central/50/ 2014 dated 24-2-2014 |
|
6 |
5983 |
12/01/2012 |
C3/489/2010 |
K.JAYAKUMAR & 7 OTHERS, No.15, Kadar Nawaz Khan Road, 4th Floor, Kakani Towers, Nungambakkam, Chennai-6 |
Dr.Ambethkar Road, Kodambakkam in T.S.No.5/28, 4/93, 4/94Part, 4/96, 4/99, 5/29Part, Block 45 of Puliyur Village. |
Puliyur |
Revised PP for the existing building of Basement Floor + Stilt Floor + 8th Floors + 9th Floor Part of Office Purpose. |
|
|
|
|
|
|
|
|
7 |
5984 |
13/01/2012 |
C3/539/2009 |
MS. GOMATHI MARIA RUTH, No.11, Somasundram Street, T.Nagar, Chennai-17 |
R.S.NO.154/6 & 154/19, Block No.13 of Egmore Village, Old Door No.18 & 19, New No.6 & 8, Vasu Street, Kilpauk, Chennai. |
Egmore |
Construction of Stilt Floor + 6 Floors + 7th Floor Part Residential Building with 26 Dwelling Units. |
2364.65 |
|
|
|
Multi-storeyed Building comprising Stilt Floor + 6 Floors + 7th Floor (Part) Residential Building with 26 Dwelling Units |
EC/CCW/N&C/ 1449/2014 |
EC/North/212/2014 dated 18-11-2014 |
|
8 |
5985 |
19/01/2012 |
C3/283/2011 |
EXECUTIVE ENGINEER & ADO, TAMIL NADU HOUSING BOARD, Special Project Division-II, Ashok Nagar, Shopping Complex, Chennai-83 |
Plot No.1, S.No.388Part, 389Part, 390, 391Part, 392Part, 393Part, 394Part, 395Part, 396Part, 397Part & 401Part of Nerkundram Village, Chennai. |
Nerkundram |
Construction of combined Basement Floor for Stilt Floor + 19th Floors (8 Blocks) with 608 Dwelling Units. |
35736.83 |
|
|
|
|
|
|
|
9 |
5986 |
25/01/2012 |
C3/18052/2010 (C3/13702/2007) |
Y.MEERA REDDY, DIRECTOR SRI KOUSALYA CONSTRUCTION LTD., No.4, Jayalakshmipuram 1st Street, Nungambakkam, Chennai-34 |
Plot No.B19Part, B20 & B21, Thiru Vi Ka Industrial Estate, Guindy in S.No.34Part, 40Part, 50Part, 62Part, Block No.6 Alandur Village. |
Alandur |
Construction of Basement Floor + Stilt Floor + 8 Floors IT / ITES Building. |
2004 |
|
|
|
|
|
|
|
10 |
5987 |
25/01/2012 |
C3/284/2011 |
THE EXECUTIVE ENGINEER & ADMIN OFFICER, TNHB, K.K.Nagar, Chennai-83 |
Plot No.2, Nerkundram, Chennai in S.No.399Part of Nerkundram Village |
Nerkundram |
Construction of Basement + Stilt + 1st to 15 Floors Residential Building with 120 Dwelling Units |
4752.66 |
|
|
|
|
|
|
|
11 |
5988 |
27/01/2012 |
C3/16212/2010 |
The EXECUTIVE ENGINEER & ADMINSTRATIVE OFFICER, Besant Nagar Division, TNHB, Chennai-20 |
S.No.291/1CPart & 291/2 of Sholinganallur Village, K.K.Salai, Chennai. |
Sholinganallur |
Construction of Stilt Floor + 13 Floors Residential Building with 117 Dwelling Units. |
|
|
|
|
|
|
|
|
12 |
5989 |
30/01/2012 |
C3/5480/2010 |
K.S.GOKUL DAS, No.216/65, Alwarpet Street, Alwarpet, Chennai-18 |
Door No.497 & 498, Poonamallee High Road, Arumbakkam, Chennai in T.S.No.3 & 4, Block No.9 of Arumbakkam Village. |
Arumbakkam |
Regularisation of Basement Floor + Ground Floor + 8 Floors Commercial Building |
3971 |
|
|
|
|
|
|
|
13 |
5990 |
31/01/2012 |
C3/282/2011 |
THE EXECUTIVE ENGINEER & ADMINSTRATIVE OFFICER, TNHB, K.K.Nagar Division, Chennai-83 |
Plot No.3, S.No.400Part & 402Part of Nerkundram Village, Chennai. |
Nerkundram |
Construction of Stilt Floor + 12 Floors (2Blocks) Residential Building with 288 Dwelling Units. |
6169.15 |
|
|
|
|
|
|
|
14 |
5991 |
01/02/2012 |
C3/14567/2010 |
OM SHAKTHY AGENCIES (MADRAS) PVT. LIMITED., No.1, Jawaharlal Nehru Road, Ekkattuthangal, Chennai-32 |
Old S.No.633/1Part, 637/1Part, 637/2, 635 & 638/1, T.S.No.11/1, 12/1, 12/3, 14/1 & 16, Block No.83 of Paruthipattu Village, Avadi Municipality, Chennai. |
Paruthipattu |
Construction of Residential Building Block-1 Stilt Floor + 10Floors with 200 Dwelling Units, Block-2 Stilt Floor + 8Floors with 208 Dwelling Units, Block-3 Stilt Floor + 8Floors +9th Floor Part with 100 Dwelling Units (Totally 508 Dwelling Units) and Block-4 Stilt Floor + 4Floors Shopping Complex. |
18470 |
|
|
|
Partial Completion Certificate Application for the construction of Group Development of Multi-Storeyed Residential building for the construction of Block No.II: Stilt Floor + 8 Floors with 208 dwelling units, (As per approved Group Development of Multi-Storeyed Residential building for the construction of Block No.I: Stilt Floor + 10 Floors with 200 dwelling units, Block No.II: Stilt Floor + 8 Floors with 208 dwelling units, Block No.III: Stilt Floor + 8 Floors + 9th Floor (part) with 100 dwelling units, totally 508 dwelling units and Block No.IV: Stilt Floor + 4 Floors Shopping Complex |
EC/CC/N-II/12089 /2015 |
C.C.No.EC/North-II/ / 416 /2015 dated 29.9.2015 |
|
15 |
5992 |
06/02/2012 |
C3/18984/2010 |
M/S.AVRN HOTELS PVT. LTD., No.12, Jawaharlal Nehru Salai, Arumbakkam, Chennai-106 |
S.No.1310/2B2, 1310/2C, 1306/2A2 (As per Patta) of Madhavaram Village, Jawaharlal Nehru Salai (IRR) Chennai |
Madhavaram |
Construction of Stilt Floor + 9 Floors Hotel Building with 133 Guest Rooms. |
4289.1 |
|
|
|
|
|
|
|
16 |
5993 |
21/02/2012 |
C3/16296/2010 |
M/S.PACE BUILDERS (M) PVT. LIMITED (GPA) B-58, Anna Nagar East, Chennai-102 |
Old S.No.223Part, 224Part, 225Part, T.S.No.113/3, 113/4 & 113/5, Block No.65 of Padi Village, Chennai. |
Padi |
Construction of Block-1 & 2 Stilt Floor + 8 Floors, Block-3, 4 & 5 Stilt Floor + 9 Floors & Block-6 Stilt Floor Part & Ground Floor Part + 8 Floors + 9th Floor Part with combined Basement Floor for Block-3, 4 & 6 for Residential purpose with 315 Dwelling Units and Departmental Store in Ground Floor of Block-6. |
12140.4 |
|
|
|
|
|
|
|
17 |
5994 |
15/02/2012 |
C3/248/2011 |
A.NARAYANAN (MANAGING DIRECTOR) HOTEL CHENNAI DELUX INTERNATIONAL PVT. LIMITED., Block No.1, Plot No.5, E-Road, Koyambedu, Chennai-6. |
Arcot Road in S.No.45/48A2, 48A3, 48A4, 48A5, 48A6, 48A7, 44/10, 44/12 & 44/14 of Karambakkam Village. |
Karambakkam |
Construction of Two Basement Floor + Stilt Floor + 8 Floors Hotel Building with Swimming Pool in 3rd Floor. |
|
|
|
|
Multi-storeyed Building comprising Double Basement Floor + Stilt Floor + 8 Floors for Hotel with Swimming Pool at 3rd Floor |
EC/CCW/N&C/ 086/2014 |
EC/Central/57/ 2014 dated 10-03-2014 |
|
18 |
5995 |
02/03/2012 |
C3/8026/2009 |
THE SUPERINTENDING ENGINEER, TAMIL NADU SMALL INDUSTRIES DEVELOPMENT CORPORATION LIMITED, Thiru-Vi-Ka Industrial Estate, Guindy, Chennai-32 |
T.S.No.115Part, 116Part, 118Part, 119Part, Block No.6, Alandur Village and T.S.No.2Part, 18/1Part, Block No.3 of Adyar village |
Alandur & Adyar |
Construction of Basement Floor + Ground Floor + Stilt Floor + First + Second Floor to 9th Floors Office Building |
|
|
|
|
|
|
|
|
19 |
5996 |
21/03/2012 |
C3/9019/2010 |
M/S.GOLDEN HOMES PVT. LTD., Door No.AC-63, 5th Avenue, Anna Nagar, Chennai-40 |
S.Nos.5/1B2, 84/2, 85, 86/1, 87, 88/1, 88/2, 89/1, 89/2A & 89/2B of Poonamallee Village, Poonamallee Bye Pass Road, Chennai |
Poonamallee |
Construction of 10Floors Viz A1, A2, C:Stilt + 17Floors, B1, B2, D, E : Stilt + 16Floors, Residential Building with 815Dwlling Units, Block F: Basement Floor + Stilt + 3 Floors Commercial Building with Gym, Games, Parlour, Banquet and Swimming Pool, Block G: Ground Floor – Departmental Store and Block H:Ground Floor – Electrical Room |
32549.12 |
|
|
|
|
|
|
|
20 |
5997 |
15/03/2012 |
C3/1914/2012 |
EXECUTIVE ENGINEER, PUBLIC WORKS DEPARTMENTS, North Residency Division, Chepauk, Chennai-5 |
Namakkal Kavignar Maligai, Secretariat, Chennai-9 |
|
Planning Clearance for the proposed face lift / External structural Improvements to the existing Multi Storeyed Building |
|
|
|
|
|
|
|
|
21 |
5998 |
22/03/2012 |
C3/14163/2011 |
M/S.I.T.C. LTD., New No.63, Old No.37, Anna Salai, Guindy, Chennai-32 |
New No.63, Old No.37, Anna Salai, Guindy, Chennai-10, T.S.No.3/3 (Old No.3/1) Block No.9 of Adyar Village |
Adyar |
Revised Planning Permission for the construction of 3 Basement Floor + Ground Floor + 8 Floors + 9th & 10th Floor Part Hotel Building (Swimming Pool at 6th & 10th Floor) |
32330 |
|
|
|
|
|
|
|
22 |
5999 |
30/03/2012 |
C3/4197/2011 |
M/S.SAS REALTORS PVT. LTD., REP BY T.V.SATHYANARAYANAN No.3, Mangesh Street, T.Nagar, Chennai-17 |
Old Door No.87, New No.134, Arcot Road, T.S.No.1/1, 1/2, Block No.43, Saligramam Village, T.S.No.268/2, Block No.32 of Virugambakkam Village, Chennai |
Saligramam, Virugambakkam |
Construction of Double Basement Floor + Stilt Floor + 17 Floors Residential Building with 166 Dwelling Units and Basement Floor + Ground Floor + 2 Floors – Service and Gym Block with Swimming Pool at Terrace Floor. |
24417.61 |
|
|
|
Multi-storeyed building with two blocks, Block-1 consisting of double basement floor + stilt floor + 17 floors residential use with 166 dwelling units and Block-2 consisting of Basement floor + ground floor + 2 floors services and Gym use with swimming pool at terrace floor. |
Letter No. EC/C-I/463/2015 |
EC/Central-I/540/2015 dated 30-12-2015 |
|
23 |
6000 |
09/04/2012 |
C3/17741/2010 |
K.RAMESH (POA) FOR DR.VASANTHI RANGARAJAN & DR.SRINIDHI KANTI CHIDAMBARAM No.11, Muktha Garden Avenue, Spur Tank Road, Chennai-31 |
Old Door No.828 & 828A, New No.268 & 268A, Poonamallee High Road, R.S.No.3125/2 & 3125/6, Block No.51 of Purasawalkam Village |
Purasawalkam |
Construction of Basement Floor Part + Stilt Floor + First Floor to 8th Floor Office Building |
2758.76 |
|
|
|
|
|
|
|
24 |
7101 |
10/04/2012 |
C3/5934/2011 |
M/S.S & S FOUNDATION PVT. LTD., No.45, Giriappa Road, T.Nagar, Chennai-17 |
S.No.69/2, 3, 4 & 5 (as per document) 69/5A1A1A, 69/2A2 (as per Patta) of Pallikaranai Village. |
Pallikaranai |
Construction of Common Basement Floor for Block A & B Stilt Part + Ground Floor Part + 13 Floors with 96 Dwelling Units – Block A (Commercial & Residential) & Stilt Floor + 13 Floors + 14th Floor Part with 107 Dwelling Units – Block B (Residential Building) Total of 203 Dwelling Units. |
24559.56 |
|
|
|
Multi-storeyed Building comprising Common Basement Floor for Block A & B with Stilt Floor (Part) + Ground Floor (Part) + 13 Floors Commercial and Residential Building with 96 Dwelling Units in Block A and Stilt Floor + 13 Floors + 14th Floor (Part) Residential Building with 107 Dwelling Units in Block B; Totally 203 Dwelling Units |
EC/S-II/1197/2015 |
EC/South-II/379/2015 dated 01.09.2015 |
|
25 |
7102 |
17/04/2012 |
C3/8153/2011 |
DR.SHANKAR T.S.R.MOHANA SELVAN No.6, Pushpa Colony, Saligramam, Chennai-93 |
R.S.No.62/4, 62/9, 62/23, 62/24. 62/32 & 62/39, Block No.2 Puliyur Village, Jawaharlal Nehru Salai (IRR) Vadapalani, Chennai |
Puliyur |
Construction of Stilt + 9 Floors Hotel Building as a revision to the earlier approved Stilt + 9Floors Office Building. |
3707.24 |
|
|
|
|
|
|
|
26 |
7103 |
17/04/2012 |
C3/4557/2010 |
SRI RAMACHANDRA EDUCATIONAL & MEDICAL TRUST, New No.24, Old No.25, Sir C.V.Raman Road, Alwarpet, Chennai-18 |
S.No.151/6, 163/5 & 6, 187/2, 188 to 221 of Ayyappanthangal Village, S.No.1 to 3 of Thelliaragaram Village, S.No.210/2Part of Vanagaram Village, S.NO.39/2 & 39/4 of Chettiaragaram Village, S.No.79/2, 80/2, 81 to 85, 86/2, 87 to 102, 103/2, 104 to 109 of Thundalam, S.No.149/2, 150/1 to 4 of Karambakkam Village, Mount Poonamallee Road, Porur, Chennai |
Ayyappanthangal, Thelliaragaram, Vanagaram, Chettiaragaram, Thundalam, Karambakkam, Porur |
Construction of additional Blocks covered in this Planning Permission of Block No.40 – Generator and MRD Room- Single Block Ground Floor + 2 Floors, Block No.41 – Ladies Student Hostel No.of Blocks -5, Ground Floor + 3 Floors, Block No.41A – Ladies Student Hostel, No.of Blocks – 4 Ground + 3 Floors, Block No.42 – Ladies Student Hostel – NRI Block – No.of Blocks _3, Ground Floor + 3 Floors, Block No.43 – Ladies Hostel II – Single Block, Ground Floor + 4 Floors, Block No.44 – Ladies Hostel I- Single Block Ground Floor + 4 Floors, Block No.45 – Visiting faculty (Staff quarters) – Single Block, Ground Floor + 2 Floors, Block No.46, Kitchen and Service Block, Single Block- Ground Floor, Block No.47 – EB Shed, (Near Nurses Hostel) Single Block – Ground Floor, Block No.48 – Store shed Singe Block – Ground Floor, Block No.49 – Pump House (Near medical College) Single Block – Ground Floor Block No.50 – College of Nursing and Sub station, Single Block _ Ground Floor + Mezzanine Floor + 3 Floors, Block No.51 – Waiting Hall single Block, - Ground Floor, Block No.52 -Canteen Block and College of Physiotherapy – Single Block Ground Floor + 4 Floors, Block No.53 – Reservation Counter, Bank and Post Office _ Single Floor, Ground Floor + 2 Floors part, Block No.54 – Meditation Hall Single Block – Ground Floor, Block No.55- Single Bed Staff Quarters – Single Block, Ground Floor + 2 Floors, Block No.56 – Dental College, Single Block, Basement Floor + Ground Floor + 4 Floors, Block No.57 - Early intervention center, _ Single Block Ground Floor + 4 Floors Block No.59- College of Pharmacy /AC plant – Single Block Ground Floor + 3 Floors, Block No.60 – Attentent waiting Hall near IP Block, Single Block Ground Floor Block No.61- AC Plant, near Dental College – Single Block, Ground Floor Block No.64 – Sub-Station III - Single Block – Ground Floor, Block No.65 - Sports Medicine Center – Single Block – Ground Floor + 3 Floors. Block No.66 and 67 _Gents and Ladies PG Hostel – 4 Blocks – Ground Floor + 7 Floors. |
|
|
|
|
|
|
|
|
27 |
7104 |
20/04/2012 |
C3/15785/2010 |
M/S. ALLIANCE PROJECTS No.556, Jeevan Annand Building, Iind Floor, Anna Salai, Chennai – 18. |
S.No.514/1D (As per Document 514/1) 514/A2, 514/1C (As Per Document 514/1A) 537/A, 538/1, 538/2, 545, 546, 589, 590, 591 , 592/1, 592/2A, and 2B(As per Document 592/2), 592/3A and 3B(As per Documents 592/3) 594/2, 561/2, (As per Document 561) 536/B, 539, 540, 541, 542 of Vetri Nagar – Canal Road, Korattur Village Chennai. |
Korattur |
Revised PP for the proposed Construction of Residential Building which consisting of combined double basement floor for Block 1 to 5 and 6and 7, Stilt Floor + 17 Floors _ Block 1, 3 and 4, Ground Floor part + Stilt Floor Part + 17 Floors, Block 2, Stilt Floor + 16 Floors + 17 Floor Part + 18Floor Part Block 5, 6, and 7, Stilt Floor + 16 Floors – Block 8, Residential building with 2026 Dwelling Units, Ground Floor + 5 Floors – Block 9 Club House. |
217860.8 |
|
|
|
Combined Double Basement Floor for Block Nos. 3, 4 & 5 - Block 3 & 4 - Stilt Floor + 17 Floors and Block - 5 - Stilt Floor + 16 Floors + 17th Floor pt + 18th Floor pt residential building with 908 dwelling units (As per approved construction of Residential building of Combined Double Basement Floor for Block 1 to 5 and 6 & 7; Stilt Floor + 17 Floors – Blocks- 1, 3 & 4; GF pt + Stilt Floor part + 17 Floors – Block – 2; Stilt Floor + 16 Floors + 17th Floor pt + 18th Floor pt Blocks 5, 6 & 7; Stilt + 16 Floors – Block – 8 Residential building with 2026 dwelling units, Ground floor + 5 Floors – Block – 9 Club House) |
EC/CCW/N&C / 21567/2011, EC/CC/N-II/6082 /2015 |
C.C.No.EC/North/154/2014 dt.24.6.2014, EC/North-II/ /342/2015 dated 11.8.2015 |
|
28 |
7105 |
20/04/2012 |
C3/18234/2010 |
A. LAKSHMI NARAYANAN No.69(Old No.35) Flat No.8, T.P Koil Street, Triplicane, Chennai – 5. |
T.S. No.2, 4/1, 4/2, 5/1, 5/2, 6/1A, 6/1B, 6/1C1, 6/1D1, 8/1A, 22/1, 23/1, 24/1, Ward – A, Block – 15 of Pallavaram Village |
Pallvaram |
Construction of Combine Basements Floor + Stilt Floor + 11 Floor (17 blocks) Residential building with 788 Dwelling Units |
71620.9 |
|
|
|
56 |
EC/S-I/6590/2015 |
Partial C.C.No.EC/South-I/471/2015 dated 06.11.2015 for Block No.A-A9. |
|
29 |
7106 |
15/05/2012 |
C3/16392/2009 |
M/S.PRINCE FOUNDATIONS LTD., (POA) No.59, Ormes Road, Kilpauk, Chennai-10 |
S.No.135/3A, 136/2B, 137, 139/2, 140/1, 2A, 2B, 3, 141/1, 2, 3, 142, 143/1, 2, 148/2 & 149 Ayyappanthangal Village, Mount Poonamallee Road, Chennai |
Ayyappanthangal |
Construction of Common Basement Floor + Block-I (Type-A) – Ground Floor / Stilt + 10 Floors, Block-2 (Type-C) – Ground Floor / Stilt + 10 Floors (1 Block), Block-3, Block-4, Block-7 (Type-B) – Ground Floor + Stilt + 9 Floors (3 Blocks), Block -5 (Type-D) – Ground + Stilt + 9 Floors, Block -6 (Type-E) – Ground Floor / Stilt + 10 Floors, Block-8 – Ground Floor + First Floor – Propose with total Dwelling Units of 626. |
22358 |
|
|
|
|
|
|
|
30 |
7107 |
15/05/2012 |
C3/8018/2011 |
M/S.S & S FOUNDATION PVT. LTD., REP BY ITS MD. S.SATHYA NARAYANAN No.45, Dr. Giriappa Road, T.Nagar, Chennai-17 |
S.No.237/2BPart, 238/1B1A, 2B1 & 4A of Porur Village, Mount Poonamallee Road (Trunk Road) Chennai |
Porur |
Construction of Basement Floor + Stilt Floor + 11 Floors Residential cum Office Building with 108 Dwelling Units and Ground Floor + First Floor + Second Floor Part Service Block with Swimming Pool in the Second Floor |
4006.33 |
|
|
|
Multi-storied Residential Building with Two Blocks comprising Basement Floor + Stilt Floor + 11 Floors Residential Building with 108 Dwelling Units & Office and Service Block comprising Ground Floor +1st Floor + 2nd Floor (Part) with Swimming Pool in 2nd Floor |
EC/CCW/N&C/ 8586/2012 |
EC/Central/226/2014 dated 26-11-2014 |
|
31 |
7108 |
12/05/2012 |
C3/3178/2010 |
M/S.MFAR HOTEL LTD., No.154, Velachery Main Road, Velachery, Chennai-42 |
Door No.154, Old No.61, Velachery Main Road, Old S.No.17/1Part, 25Part, 26/1, T.S.No.17/2, 20, 21, Block No.22 of Velachery Village, Chennai |
Velachery |
Revised PP for the Proposed construction of Triple Basement Floor + Ground Floor + Service Floor + First Floor + Service Floor + Second Floor to 9th Floor – Hotel Building with open swimming Pool in the Second Floor Terrace level. |
7792 |
|
|
|
Multi-storeyed Building comprising Triple Basement Floor + Ground Floor + Service Floor + 1st Floor + Service Floor + 2nd Floor to 9th Floor Hotel Building with open Swimming Pool in the 2nd Floor Terrace level. |
ES2/9454/2012 |
EC/South/246/2012 dated 21-12-2012 |
|
32 |
7109 |
15/05/2012 |
C3/18985/2010 |
K.KRISHNAN POA OF T.A.S. JAWAHAR AYYA , No.63, G.N.Chetty Road, T.Nagar, Chennai-17 |
Plot No.B, 4th Avenue, Shanthi Colony, Anna Nagar in T.S.No.4/17, Block No.9C, Naduvakkarai Village. |
Naduvakkarai |
Construction Triple Basement + Stilt Floor Part + Ground Floor Part + 8 Floors + 9th Floor Part Building for Residential use with 32 Dwelling Units Gymnasium & Swimming Pool. |
3060 |
|
|
|
|
|
|
|
33 |
7110 |
15/05/2012 |
C3/5458/2011 |
M/S.V.G.N.PRAGNYA REALITY PVT. LTD., No.43/14, 3rd Floor, Hameedia Center, Haddows Road, Nungambakkam, Chennai-6 |
T.S.No.8/1, 9/2, 9/3, 9/5, 9/6. 9/7. 9/8 & 9/10, Block No.83, Ward-I, Avadi Municipality, Old S.No.629/1B1, 1B2, 3, 4A, 5A, 5B1, 5B2, 6B1, 6B2, 6B3 & 631/1B of Paruthipattu Village, Avadi – Poonamallee Road, Chennai |
Paruthipattu |
Construction combined Basement Floor + for Block A, B, C & D Residential Building with 781 Dwelling Units, Block A, B, C Stilt + 14 Floors, Block-D (Club House) Ground Floor + 2 Floors & Block-E (LIG) Stilt + 13 Floors |
22620 |
|
|
|
|
|
|
|
34 |
7111 |
16/05/2012 |
C3/9897/2011 |
M.CHANDRU GPA, No.17/35, 2nd Main Road, Gandhi Nagar, Adayar, Chennai-20 |
Kalaingar Karunaneedhi Salai in S.No.277/1 (Document) 277/1A (asper Patta) of Sholinganallur Village, Chennai |
Sholinganallur |
Revised Planning Permission for the Proposed Construction of Basement Floor Part + Stilt Floor + 9 Floors Residential Building with 63 Dwelling Units |
2300.87 |
|
|
|
|
|
|
|
35 |
7112 |
16/05/2012 |
C3/9898/2011 |
M/S.TEN SQUARE PROPERTY DEVELOPERS PVT. LTD., VINOTH BATHIJA (GPA) TEN'S MAY FLOWER, New No.24, Old No.18, Nageswara Road, Nungambakkam, Chennai-34 |
Mount Poonamallee Road in S.No.34/1A1B, 1A1C, 1A1D of Manapakkam Village, Chennai |
Manapakkam |
Proposed Construction of Stilt Floor + 8 Floors Residential Building with 104 Dwelling Units |
3358.87 |
|
|
|
Multi-storeyed Building comprising Stilt Floor+ 8 Floors Residential Building with 104 Dwelling Units. |
EC/C-II/18793/2014 |
Completion Certificate No. EC/C-II/244/2015 dated 19-05-2015 |
|
36 |
7113 |
25/05/2012 |
C3/6745/2011 |
D.ELUMALAI, (OWNER & POA) PROF. FOR M/S.SRINIVAS CONSTRUCTION, No.1, Thilak Street, T.Nagar, Chennai-17 |
S.No.31/2A1Part & 34/1 (As per Document), S.No.31/2A1A, 31/2A1B & 34/1 (As per Patta) Medavakkam – Sholinganallur Road (Perumbakkam Main Road), Perumbakkam Village. |
Perumbakkam |
Proposed Construction Stilt Floor + First Floor (Office) + 2nd Floor to 8th Floor Residential Building with 39 Dwelling Units. |
|
|
|
|
|
|
|
|
37 |
7114 |
25/05/2012 |
C3/6471/2010 |
M/S.BRIGADE ENTERPRISES LTD., (GPA) No.25, Vellalar Street, Kodambakkam, Chennai-24 |
S.No.284/21A1, 21A2, 21B, 21C, 21D, 21E, 22B1 & 23A of Kottivakkam Village, OMR, Chennai |
Kottivakkam |
Proposed Construction Double Basement + Ground + 3 Floors Commercial Building with 16.90m height |
|
|
|
|
Double Basement + Ground floor +3 Floors Commercial Building with 16.90m. Height. |
EC/SI/8191/2015 |
EC/South-I/372/2015 dated 25-08-2015 |
|
38 |
7115 |
28/05/2012 |
C3/4606/2011 |
M/S.PRESTIGE ESTATES PROJECTS LTD., No.117, Thiyagaraya Road, Citi Towers, 7th Floor, T.Nagar, Chennai-17 |
S.Nos.1/1, 1/2, 2, 3/1, 3/2, 3/3, 5/1, 8/2A, 35, 42/1, 42/1A, 42/1B, 42/2, 42/3A, 3B, 4, 5, 43/1, 2, 44/1A, 1B, 44/2, 3, 45/1A, 1B, 45/2, 3, 4A, 4B, 46/1, 2, 3, 47/1E, 48/1A, 1B, 2, 3, 4, 49/1, 2, 3, 50/1A, 1B, 2, 3, 4, 51/1APart, 51/1B1, 1B3, 1C1, 1C3, 1D, 1E, 52/1, 2, 53 & 54/1Part of Ayyappanthangal Village, Mount Poonamallee Road, Chennai |
Ayyappanthangal |
Proposed Construction of 33 Blocks (Type-A – 18 Nos., Type-B – 8Nos, Type-C – 4Nos, Type-D – 3Nos.) of Ground Floor + 16 Floors Residential Buildings with 2610 Dwelling Units and Common Lower Basement Floor + Upper Basement Floor Connecting (I) A1 to A4, A10 to A18, B1, B6 to B8, C1 & C4 (ii) A5, B2 to B4 & C3 & (iii) A6 to A9, B5, C2 & D1 to D3 & Club House Block with Basement Floor + 2Floors. |
|
|
|
|
MSB of 14 Blocks (A5, A6, A7, A8, A9, B2, B3, B4, B5, C2, C3, D1, D2 & D3) out of 33 Blocks – Combined Double Basement floor -II connecting the Blocks A5, B2, B3, B4 & C3; Combined Double Basement floor -III connecting the Blocks A6, A7, A8, A9, B5, C2, D1, D2 & D3 + Ground floor + 16 floors residential building with 1346 Dwelling Units in which the Block D1 to D3 with 603 Dwelling Units is reserved for LIG housing. |
EC/C-I/4841/2015 |
Partial Completion Certificate No. EC/Central-I/04/ 2016 dated 08-01-2016 |
|
39 |
7116 |
18/06/2012 |
C3/2046/2012 |
THE EXECUTIVE ENGINEER, Public Works Department, |
Omandur Government Estate, Anna Salai, Jagajeevanaran Road (Wallajah Road) Swamy Sivanananda Salai (Adams Road) Chennai |
Triplicane |
Planning Clearance for the proposed change to use from Assembly building to Multi Super Specility Hospital - Ground Floor + 6 Floors |
|
|
|
|
|
|
|
|
40 |
7117 |
22/06/2012 |
C3/11496/2010 |
M.CHANDRU " Sruthi" No.11, Second Main Road, Gandhi Nagar, Chennai-20 |
Door No.18/1, East Coast Road, S.No.205/3Part, 4A, 5A, 8 & 10, T.S.No.26, Block No.42 of Thiruvanmiyur Village, Chennai |
Thiruvanmiyur |
Planning Permission for the proposed construction of Stilt Part + Ground Floor Part + 11 Floors with 64 Dwelling Units Annexing to the existing Basement Floor + Ground Floor + 4 Floors Residential Building with 18 Dwelling Units and Commercial Building |
|
|
|
|
|
|
|
|
41 |
7118 |
25/06/2012 |
C3/6068/2011 |
M/S.LANCOR HOLDINGS LTD., Rep by Tmt.Mallika Ravi, No.58, G.N.Chetty Road, V.T.N.Square Second Floor, T.Nagar, Chennai-17 |
S.No.152Part, New S.No.152/4B & 152/5A1A1B of Valasaravakkam Village at Door No.7, Arcot Road, Alwarthirunagar, Chennai-87 |
Valasaravakkam |
Proposed construction of Common Basement + Common Stilt Floor & First Floor to 12 Floors + 13th Floor Part for Block-I and First Floor to Eight Floor + 9th Floor Part for Block-II with 65 Dwelling Units and Swimming Pool at First Floor level. |
3382.18 |
|
|
|
|
|
|
|
42 |
7119 |
26/06/2012 |
C3/6069/2011 |
LALITHA SRINIVASAN &OTHER, New No.12, Old No.312, 8th Sector, K.K.Nagar, Chennai-78 |
Plot No.L-4, Dr.Vikram Sara Bai Instronic Estate, Thiruvanmiyur, Chennai in S.No.19, 21 & 22Part, T.S.No.5, Block No.8 of Thiruvanmiyur Village. |
Thiruvanmiyur |
Planning Permission for the proposed construction of Stilt + 3 Floors + 4th Floor Part IT-Office Building. |
494.7 |
|
|
|
|
|
|
|
43 |
7120 |
27/06/2012 |
C3/7128/2011 |
M/S.SABARI FOUNDATION, No.K-67, Anna Nagar East, Chennai-102 |
S.No.760 & 761 of Kuttambakkam Village |
Kuttambakkam |
Planning Permission for the proposed additional construction of 4th Floor College Building over existing and already approved Ground + 3 Floors |
|
|
|
|
|
|
|
|
44 |
7121 |
02/07/2012 |
C3/10275/2010 |
M/S. YESES HOTES PVT. LTD., (LEASEE) REP BY ITS M.D.S.KHAJA MOHIDEEN, No.191-C, 8th Avenue, 100Feet Road, Anna Nagar West Extn., Chennai-101 |
S.No.10/3A1A1 & 17/1A of Vanagaram Village, N.H. Bye Pass Road |
Vanagaram |
PPA for the construction of Basement Floor + Stilt Floor Part + Ground Floor Part + 9 Floors + 10th Floor Part Hotel Building with 85 Guest Rooms, Banquet, Restaurant and Swimming Pool in Terrace Floor |
2787.38 |
|
|
|
|
|
|
|
45 |
7122 |
04/07/2012 |
C3/15344/2010 |
M/S.SELENE ESTATE LTD., No.68/1A, Perumbakkam - Jalladianpettai, Joint Road, Jalladianpettai, Chennai-100 |
S.No.62/2C2, 3, 63/1, 2A, 2B, 64/1B, 2A, 2B, 65/1B, 2, 66/1, 2, 67, 68/1A, 2A2, 3, 69/1A, 1B, 1C, 2, 3A, 3B, 3C, 70/1 to 8, 71/1, 2, 3, 5A, 5B2, 74/1C, 4, 75/1, 2, 3A, 3B, 3C, 3D, 75/4, 5, 6A, 6B, 6C, 6D, 76/1A, 1B, 1C, 76/2, 3, 5B, 77/2A, 2B, 80/3E1, 3E2, 81/5B, 82/1, 2 of Jalladianpettai Village |
Jalladianpettai |
PP for the proposed construction of connected Basement Floor + Ground Floor + 6 Floors for Block A1, A2, A3, B1, B2, B3, B4, C1, B5, B6, C2, C3, Connected Basement Floor + Stilt Floor + 7 Floors for Block D1, D2, D3, E1, E2, E3, E4, E5, E6, E7, F, Stilt + 7 Floors for EWS1, EWS2 with 843 Dwelling Units and Club House with Ground Floor + 2 Floors Commercial Block of Ground Floor + 6 Floors |
62628 |
|
|
|
|
|
|
|
46 |
7123 |
05/07/2012 |
C3/12583/2011 |
T.V.SATHYA NARAYANA, No.3, Mangesh Street, T.Nagar, Chennai-17 |
S.No.143/429 of Pammal Village at Mahathma Gandhi Road, Sri Sankara Nagar, Pammal, Chennai |
Pammal |
PP for the proposed construction of Service Block of Basement Floor (Gym) + Ground Floor Part (Swimming Pool) in between 2 Blocks Stilt + 11 Floors Residential Building with 121 Dwelling Units (Block 1 - 66 Dwelling Units, Block 2 - 55 Dwelling Units) |
4545.33 |
|
|
|
Multi-storeyed Building comprising Service Block of Basement Floor (Part) (Gym) + Ground Floor (Part) Swimming Pool in between 2 Blocks of Stilt Floor + 11 Floors Residential Building with 120 Dwelling Units (As per approval 121 Dwelling Units) i.e. Block No.1:66 Dwelling Units and Block No.2:54 Dwelling Units. |
EC/CCW/S/2138/2013 |
EC/South/127/ 2014 dated 23-05-2014 |
|
47 |
7124 |
09/07/2012 |
C3/15949/2011 |
A.G.RANGANATHAN |
Plot No.32, Old S.No.2Part, 9Part & 10Part, T.S.No.9/5 & 10/8, Block No.2 of Alandur Village, Thiru.Vi.Ka. Industrial Estate, IRR, Guindy, Chennai |
Alandur |
PPA is for the proposed construction of Basement Floor + Stilt Floor + 6 Floors Electrical & Electronic Industry cum Office |
1828.07 |
|
|
|
|
|
|
|
48 |
7125 |
20/07/2012 |
C3/2998/2011 |
HITESH KAWAD (MD) SPR & RG CONSTRUCTION PVT. LTD., |
S.No.137/1, 138/1, 148/5A & 148/7A at Bye Pass Road, Karambakkam Village, Porur, Chennai |
Karambakkam |
PPA is for the proposed construction of Residential Building of combined Basement 1 & 2 + Ground Floor + 14 Floors of Block 1 to 9 with 950 Dwelling Units |
35786.5 |
|
|
|
|
|
|
|
49 |
7127 |
24/07/2012 |
C3/4433/2011 |
HARESH KISHORE GF.No.5, Bishop Wallers Avenue (East) Mylapore, Chennai-4 |
Old S.No.265/3Part, T.S.No.27/1A, Ward-F, Block 17 of Adambakkam Village at IRR Chennai. |
Adambakkam |
PPA is for the proposed construction of Stilt Floor + 9 Floors Office Building |
1706.42 |
|
|
|
|
|
|
|
50 |
7128 |
26/07/2012 |
C3/19053/2009 |
THE SUPERINTENDING ENGINEER, CDC/TANTRANSCO, A-10, Thiru-Vi-Ka Industrial Estate, Chennai-32 |
R.S.No.20/1, Block No.3 of Nungambakkam Village, New No.144, Anna Salai, Chennai |
Nungambakkam |
PPA for the proposed additional construction of 230KV Genset sub-station and TANTRANSCO Office, Block Basement Floor + Ground Floor Part + Stilt Floor Part + First Floor to 6th Floor Part + First Floor to 6th Floor to the earlier Approved buildings. |
|
|
|
|
|
|
|
|
51 |
7129 |
25/07/2012 |
C3/5359/2011 |
M/S.LANCOR HOLDINGS LTD., Rep by CEO, Mrs.Mallika Ravi, No.58, Lin Chetty Street, T.Nagar, Chennai-17 |
New No.3, Old No.19, 3rd Main Road, Ram Nagar, Nanganallur in Old S.No.97/15 of Adambakkam Village T.S.No.53, Block No.15, Ward No.E of Alandur M.P. Chennai |
Adambakkam |
PPA is for the Proposed construction of Stilt + 6 Floors + 7th Floor Part Residential Building with 64 Dwelling Units |
4233.17 |
|
|
|
Multi-storeyed Building comprising Stilt Floor + 6 Floors + 7th Floor (Part) Residential Building with 64 Dwelling Units |
EC/CCW/S/ 20153/2012 |
EC/South/86/2014 dated 10-04-2014 |
|
52 |
7130 |
27/07/2012 |
C3/4516/2008 |
U.KARUNA SESH, No.22, Rajaram Metha Nagar, Chennai-29 |
S.No.413/2, 418/1A2, 2B, 420/1B, 1C, 421/3A, 3B, 418/1A3 & 412/2C of Ambathur Village, MTH Road, Ambathur Industrial Estate, Ambathur Taluk, Chennai |
Ambathur |
PPA for the Construction of Stilt + 10 Floors IT Building and Ground Floor + First Floor Service Block |
11147.42 |
|
|
|
|
|
|
|
53 |
7131 |
31/07/2012 |
C3/7448/2010 |
M/S.JONES FOUNDATION PVT. LTD., No.2, Moovarasampet Main Road, Madipakkam, Chennai-91 |
S.No.170/1A1F2, 1B, 2B, 1C1, 1C2, 2C1, 2C2, 172, 173/1A1, 1A2, 1B1, 1B2, 1C, 1D, 1E, 2 of Pallikaranai Village, Chennai |
Pallikaranai |
PP is for the Proposed Construction of Block A- Stilt Part + Ground Floor Part + 6 Floors + 7th Floor Part 63 Dwelling Units, Block B - Stilt + 7Floors 84 Dwelling Units, Block C - Stilt + 7 Floors 56 Dwelling Units, Block D - Stilt + 7 Floors 28 Dwelling Units, Block No. E - Stilt + 7 Floors 56 Dwelling Units, Club House - Ground Floor + First Floors (Total No. of Dwelling Units 329) |
20887.83 |
|
|
|
construction of Group Development of Block A – Stilt (pt.)/ GF (pt.) + 6 Floors + 7th Floor (pt.) – 63 Dwelling units; Block B- Stilt + 7 floors- 70 dwelling units; Block C- Stilt + 7 floors- 28 dwelling units; Block D- Stilt + 7 floors- 84 dwelling units; Block E- Stilt + 7 floors- 56 dwelling units; Block F- Stilt + 7 floors- 28 dwelling units; Club House – GF+ 1 Floor (Total 329 DUs) in S.No. 170/1A1F2, 1B, 2B,1C1, 1C2, 2C1, 2C2, 172,173/1A1, 1A2, 1B1,1B2, 1C, 1D, 1E, 2 of Pallikaranai Village, Chennai |
EC/S-II/20260/2015 |
EC/South-II/17/2016 dated 25.01.2016 |
|
54 |
7132 |
02/08/2012 |
C3/770/2011 |
M/S.PACE BUILDERS (M) PVT. LIMITED (GPA) B-58, Anna Nagar East, Chennai-100 |
Door No.5/391, Tambaram - Velachery Road, Ranganathapuram, Chennai-601 302 in S.No.392/1A & 1B (as per Document) S.No.392/1A2, 1A3, 1A4 (as per Patta) of Medavakkam Village, Chennai |
Medavakkam |
PP is for the Proposed Construction of Basement Floor + Stilt + 11 Floors for Residential use with 66 Dwelling Units and Basement Floor + Stilt + 10 Floors for Office use in a single block. |
3924.1 |
|
|
|
|
|
|
|
55 |
7133 |
03/08/2012 |
C3/7401/2011 |
P.BHAVANI, Door No.802 & 804, Anna Salai, Nandanam, Chennai-35 |
Kundrathur Main Road in S.No.96/1, 96/2A1, 2A2, 2A3 of Gerugambakkam Village |
Gerugambakkam |
PP is for the Proposed Construction of Stilt Floor Part / Ground Floor Part + 8 Floors Departmental Store cum Residential Building with 80 Dwelling Units (Swimming Pool in Ground Floor) |
|
|
|
|
|
|
|
|
56 |
7134 |
07/08/2012 |
C3/5299/2010 |
M/S.GODREJ SEA VIEW PROPERTIES LTD., 8th Floor, West Minister Building, No.70, R.K.Salai, Mylapore, Chennai-4 |
S.No.157/2, 158/2, 3, 4, 5, 6, 7, 8, 162/2, 163/2, 3, 4, 5, 6, 7, 8, 170/4, 5, 6, 7, 178/6A, 181/1, 2A, 2B, 2C, 2D, 3, 4, 5, 6, 7, 13, 182/1, 2, 3 & 11 of Chembarambakkam Village |
Chembarambakkam |
PP for the Proposed Construction of Residential Apartments with 7 Towers- and Club House connected by Common Podium (Ground / Stilt) Tower 1 & 2 - First Stilt + 17 Floors, Tower 3 (Exclusive for EWS) First Stilt + 17 Floors, Tower 4 - First Stilt + 15 Floors, Tower 5 & 6 - First Stilt + 17 Floors, Tower 7A & 7B - First Stilt + 17 Floors, Tower 7C, 7D, 7E, 7F, 7G & 7H - First Stilt + 18 Floors & Club House, First Stilt + 3 Floors |
70412.99 |
|
|
|
|
|
|
|
57 |
7135 |
24/08/2012 |
C3/5023/2010 |
PRASHANTH S.KHARCHE 12/20, Safi Mohammed Road, Chennai-6 |
Thulakattamman Koil Thottam, Rajiv Gandhi Salai (OMR) in S.No.478/2B of Sholinganallur Village, Chennai |
Sholinganallur |
PPA is for the Proposed construction of Basement Floor + Stilt + 10 Floors (Office Use) Basement Floor + Stilt + 11 Floors (Hotel Use) in a Single Block |
11622.88 |
|
|
|
|
|
|
|
58 |
7136 |
31/08/2012 |
C3/408/2012 |
M/S.REED RELAYS & ELECTRONICS INDIA LTD., REP BY S.K.PETER, No.17/35, Second Main Road, Gandhi Nagar, Adayar, Chennai-20 |
No.11, Old Mahabalipuram Road, Old S.No.117/2B & 118/2, New S.No.117/5A, 1A & 118/7A2 of Okkiam Thoraipakkam Village |
Okkiam Thoraipakkam |
PPA is for the Proposed Construction of Stilt + 6 Floors Show Room & Office, Basement Floor + Stilt + 17 Floors Residential Building (109 Dwelling Units) |
6304.79 |
|
|
|
|
|
|
|
59 |
7137 |
06/09/2012 |
C3/4621/2011 |
AJAY LUNAWATH (GPA) 5C, Ega Trade Center, No.809, Poonamallee High Road, Kilpauk, Chennai-10 |
Door No.30, New No.73, West Jones Road, Saidapet in Old S.No.242/2Part, 242/1Part, T.S.No.212/6, Block No.85 of Kodambakkam Village. |
Kodambakkam |
Revised PP for the Construction of Stilt + 7 Floors (Block 1 to 5), Stilt + 4 Floors (Block 6) Residential Building with 130 Dwelling Units |
8825.97 |
|
|
|
|
|
|
|
60 |
7138 |
06/09/2012 |
C3/13119/2010 |
M/S.VIJAYA PRODUCTIONS PVT. LTD., Door No.183, N.S.K. Salai (Arcot Road), Vadapalani, Chennai-26 |
Door No.183, N.S.K.Salai (Arcot Road) Vadapalani, Chennai-26 in T.S.No.5/1, 5/3, 5/4 & 5/5, Block No.5 of Saligramam Village |
Saligramam |
PPA is for the Proposed Construction of Additional Block of 3 Basement Floor + Ground Floor + 4 Floors (27.50m Height) in th front side of the building, 3 Basement Floor + Ground Floor + 5th Floor Part (27.50m Height) in the middle of the building, 3 Basement Floor + Ground Floor + 11 Floors (45.75m Height) and 3 Basement Floor + Ground Floor + 10 Floors (MLCP) + 3 Floors (Office above MLCP) (45.75m Height) in the rear of the Commercial Building (Shopping Mall, Theatre - 9 Nos. Restaurant, Office and MLCP) and Regularisation of the existing 2 Basement Floor + Ground Floor + MF + First Floor to 6th Floor Hotel Building |
58398.7 |
|
|
|
|
|
|
|
61 |
7139 |
07/09/2012 |
C3/1132/2010 |
T.V.SATHYA NARAYANA, No.16/22, Arulambal Street, T.Nagar, Chennai-17 |
No.45, Tambaram - Velachery Main Road, Pallikaranai, Chennai-601302 at S.No.546/2B, 560/1B, 561/2, 1A2, 561/1B, 1C, 562/1, 2, 3, 563, 567, 568, 571/2, 3 of Pallikaranai Village |
Pallikaranai |
PPA is for the Proposed Construction of Common Basement Floor (Block A to G), Block A - Ground Floor / Stilt + 12 Floors (96 Dwelling Units) Block B - Ground Floor + Stilt + 12 Floors (96 Dwelling Units), Block C - Ground Floor / Stilt + 10 Floors + 11th Floor Part (84 Dwelling Units), Block D- Ground Floor / Stilt + 12th Floor Part (94 Dwelling Units), Block E- Ground Floor / Stilt + 12 Floors (48 Dwelling Units), Block F- Ground Floor + 2nd Floor Part (Non FSI Area) Block G- Ground Floor + 10 Floors + 11th Floor Part (93 Dwelling Units) Open Transformer, Gen Set, STP-Total Number of Dwelling Units 511 |
17926.98 |
|
|
|
Multi-storeyed Building comprising Basement Floor - Upper and Lower 2 Levels - (Block AtoG); Block-A: Ground Floor/Stilt Floor + 12 Floors with 84 Dwelling Units; Block-B: Ground Floor/Stilt Floor + 12 Floors with 84 Dwelling Units; Block-C: Ground Floor/Stilt Floor + 10 Floors + 11th Floor (Part) with 74 Dwelling Units; Block-D:Ground Floor/Stilt Floor + 12 Floors with 82 Dwelling Units; Block-E:Ground Floor/Stilt Floor + 12 Floors with 48 Dwelling Units; Block-F:Ground Floor + 1st Floor + 2nd Floor (Part) [Non-FSI] and Block-G: Ground Floor + 10 Floors + 11th Floor (Part) with 93 Dwelling Units; Totally 465 Dwelling Units. |
EC/CCW/S/3328/ 2014 |
EC/South/197/ 2014 dated 31-10-2014 |
|
62 |
7140 |
29/09/2012 |
C3/4432/2011 |
B.RAGHAVENDRA REDDY, C/O, SRINIVASA ENTERPRISES, 38/74, Bazulla Road, T.Nagar, Chennai-17 |
Door No.1/609, OMR (Rajiv Gandhi Salai) and MMRD Road in S.No.69/5A1, 5A2, 6A1, 6A2 of Okkiam Thoraipakkam Village |
Okkiam Thoraipakkam |
Revised PP is for the Proposed Construciton of 3 Basement Floor + Ground Floor + 5 Floors Shopping Mall and Multiplex Theatre (8Nos.) Commercial Building |
4350 |
|
|
|
|
|
|
|
63 |
7141 |
08/10/2012 |
C3/18882/2010 |
J.SENTHIL KUMAR, No.41, Giri Road, T.Nagar, Chennai-17 |
R.S.No.51/1A2, 1B, 52/1 of Korattur Village, Poonamallee P.U. |
Korattur |
PP Additional Construction of 4th to 8Floor and extention of Ground Floor + 2 Floors on rear side to the earlier Approved Basement Floor + Ground Floor + 3rd Floor Hostel Block (Block -D) |
37650 |
|
|
|
|
|
|
|
64 |
7142 |
09/10/2012 |
C3/11499/2010 |
V.S.SARAVANAN, No.17-1, Poes Road Second Street, Teynampet, Chennai-18 |
R.S.No.4274/42, 43, 12, 13 & 14, Block No.93, Mylapore Village at Door No.20L, Greenways Road, R.A.Puram, Chennai |
Mylapore |
PPA is for the Proposed Construction of Second Basement Floor + First Basement Floor + Stilt Floor + 9Floors Residential Building (18 Dwelling Units) |
2347.26 |
|
|
|
|
|
|
|
65 |
7143 |
10/10/2012 |
C3/18895/2011 |
M/S.MALLES CONSTRUCTIONS PVT. LTD., Director Mr.U.Chandra Prakasam, No.19, Tanjore Road, T.Nagar, Chennai-17 |
Sholinganallur Main Road, S.No.30/1A1, 1A2C, 1A3, 1B3 & 1C2 of Perumbakkam Village, Chennai |
Perumbakkam |
PPA is for the Proposed Construction of Basement Floor + Stilt Floor + First Floor (Commercial Area) + Second to 14th Floor (Residential) with 78 Dwelling Units + 15th Floor (Gym & Swimming Pool) |
2471.13 |
|
|
|
Multi-storeyed Building comprising Basement Floor + Stilt Floor + 1st Floor (Commercial area) + 2nd Floor to 14th Floor (Residential) with 78 Dwelling Units + 15th Floor (Gym and Swimming Pool) |
EC/S-II/9504/2015 |
EC/South-II/386/2015 dated 04.09.2015 |
|
66 |
7144 |
10/10/2012 |
C3/194/2011 |
BHARATH KUMAR .K. KAMDAR (POA) Prince Apartments, No.59, Ormes Road, Kilpauk, Chennai-10 |
OMR (Rajiv Gandhi Salai) Sholinganallur in S.No.476/3, 2A1, 2A2, 4A2, 5A1, 5A2 & 35 |
Sholinganallur |
PPA is for the Proposed Construction of combined Basement Floor (Block-1 to 4) + Stilt Floor + First Floor to 17th Floor (4 Blocks), LIG Blocks of Stilt + 4 Floors Residential Flats with 498 Dwelling Units & Basement Floor + Ground Floor + First Floor for Club House |
24162.38 |
|
|
|
|
|
|
|
67 |
7146 |
17/10/2012 |
C3/17444/2011 |
A.T.ANSARI (POA) REP BY S.P.BALASUBRAMANIAN, No.18/37, Maharaja Suriya Road, Alwarpet, Chennai-18 |
Old S.No.198/7, T.S.No.95, Block No.43 of Salaigramam Village, Door No.75, Arcot Road, Chennai |
Saligramam |
PPA for the Construction of Stilt + 8 Floors + 9th Floor Part Residential Building with 32 Dwelling Units Gym & Swimming Pool at 9th Floor |
1602.84 |
|
|
|
|
|
|
|
68 |
7147 |
22/10/2012 |
C3/687/2011 |
M/S.CHAITANYA BUILDERS LEASING PVT. LTD., Kakani Towers, No.15, Kadhar Nawaskhan Road, Chennai-6 |
R.S.No.3818/5, 7, 9, 15 & 18, Block No.75 of Mylapore Village at Door No.1/104-BB, Anna Salai, Teynampet, Chennai |
Mylapore |
PPA is for the Proposed Construction of 2 Blocks - Office use Commercial Building - Block- A Basement Floor + Stilt + 10 Floors for Office use & Block-B Basement Floor + Stilt + 4 Floors for Office Use |
|
|
|
|
2 Blocks office use commercial building Block-A(MSB) consisting Basement Floor+Stilt Floor +10 Floors and Block-B consisting Basement Floor+Stilt floor +4 Floors |
EC/C-II/9319/2015 |
Completion Certificate No. EC/Central-II/358/2015 dated 17-8-2015 |
|
69 |
7148 |
01/11/2012 |
C3/16777/2010 |
M.RAVI, M.KANNAN & ICMC CORPORATION LTD No.27, Elango Nagar, Kottivakkam(Opp) OMR Chennai - 41. |
S.No.12/5, 13/1A1A, 1A1B, 1A1D, 1A1E, 1A1F, 1A1G, 1A1H, 14/1A1, 1A2, 1A3, 1A4, 1A5, 1A6, 1A7, 1A8 of Rajakilpakkam Village, Velachery Main Road, Chennai. |
Rajakilpakkam |
PPA is for the Construction of combined basement floor + Stilt, First to 14 Floors of Block A to C Residential Building ( 364 Dwelling Units and Ground Floor + First Floor of Block D, Meter Room and Gym. |
11339.91 |
|
|
|
|
|
|
|
70 |
7149 |
Cancelled |
|
|
|
|
|
|
|
|
|
|
|
|
|
71 |
7150 |
12/11/2012 |
C3/2427/2010 |
M/S. A.G.CLOTHING LTD, M.D Dr. S.K.GUPTA No.26 & 27 Morison Ist Street, Alandur, Chennai - 16. |
Plot No.8, Thiru-Vi-Ka Industrial Estate in Old T.S.No.12pt, New T.S.No.164, Block No.5, Alandur Village, Chennai. |
Alandur |
PPA is for the Proposed Construction of Double Basement Floor + Stilt + 2 Floor (Parking) + 3rd to 10th Floor for IT Use |
- |
|
|
|
|
|
|
|
72 |
7151 |
21/11/2012 |
C3/3250/2011 |
M/S.ANJALI INFRA HOUSING LLP REP BY SIDDHARTH MAHER No.25, Burnaby Road, Kilpauk, Chennai -10. |
S.No.34/2pt & 37pt, T.S.No.2/2, Bk no.12, Padi Village, Chennai. |
Padi |
PPA is for the Proposed construction of Combined Basement floor + Bk 1 - Stilt floor + 15 floors Residential blg (120 D.Units), Bk 2 - Stilt + 15 floors Residential blg (135 D.units) and Ground floor + 1st floor Block for Service and Gym & Open swimming pool in 1st floor. |
9721.51 |
|
|
|
|
|
|
|
73 |
7152 |
Cancelled |
|
|
|
|
|
|
|
|
|
|
|
|
|
74 |
7153 |
26/11/2012 |
C3/10942/2011 |
M/S. PRINCE FOUNDATIONS LTD., REP BY THIRU ASWIN KUMAR K KAMDAR , PRINCE APARTMENTS. No.59, Ormes road, Kilpauk, Chennai - 10. |
R.S.No.679/1, 2&3, Bk no.16, Vepery Village, D.No.44/172, EVK Sampath salai, Vepery, Chennai. |
Vepery |
PPA is for the proposed construction of Bk A - Stilt + 10 floors & Bk B - Stilt + 9 Floors +10th floor part with combined double basement residential blg with 49 D.Units and Gymnasium. |
3987.74 |
|
|
|
|
|
|
|
75 |
7154 |
27/11/2012 |
C3/10196/2011 |
M/S. MADRAS RADIATORS & PRESSING LTD., REP BY THIRU.N.JAYARAMAN (GPA) |
D.No.129, CTH Road, Old S.No.23 pt, 24, 25, 26, 27/1, 2, 3, 4 & 43/1, T.S.No.33/1, Bk no.84, Ward B, Ambattur Village, Chennai |
Ambattur |
PPA is for the proposed construction of Bk 1 - Stilt + 16 Floors (352 D.Units) Bk 2 - Stilt + 13 Floor + 14th Floor pt with 82 D.units for LIG, Commercial Block - GF + 2F + 3F part with swimming pool at Terrace and multi level car parking. |
16683 |
|
|
|
Block-I- Stilt Floor + 16 Floors with 352 dwelling units, Block – II - Stilt Floor + 13Floor + 14th Floor part with 82 dwelling units for LIG; Commercial Block: GF+2F+3rd Floor part with Swimming Pool at terrace and Multi Level Car parking Block; Stilt Floor + 2 Floors |
EC/CC/N-II/8788/2015 |
C.C.No.EC/North-II/ /336/2015 dated 7.8.2015 |
|
76 |
7155 |
23/11/2012 |
C3/2217/2011 |
M/S. TRUE VALUE HOMES INDIA PVT LTD., Block no.94, TVH Beliciaa Tower, Tower-II, 9th Floor, MRC Nagar, R.A.Puram, Chennai - 28. |
River View Road, Kotturpuram in T.S.No.8/14, 7/80 & 7/81, Bk no.16 of Adyar Village. |
Adyar |
PPA is for the proposed construction of 4 Block combined double basement floor for 4 block (Mezzanized parking) A Block - GF+16 Floors + 17th Floor part (34 D.Units), Block B - GF+16 Floors + 17th Floor Part ( 32 D.Units), Block C - GF+16Floors + 17th Floor part (25 D.Units), Block D - GF+15 Floors (83 D.Units) Residential development with 174 D.Units and Incidental use at Ground floor in all block and Swimming pool in the space adjacent to Block A. |
13446.6 |
|
|
|
|
|
|
|
77 |
7156 |
30/11/2012 |
C3/21266/2011 |
THIRU.PRAVEEN KUMAR GUPTA (GPA) C/O. SRINIVASA ENTERPRISES, MASS TOWER 1ST FLOOR , No.38/74, Bazullah road, T.Nagar, Chennai-17. |
T.S.No.7, Block no.10, Ward E of Ambattur, Old S.No. 750/5A of Korattur village, D.No. 243, Red hills Road, Kalikuppam, Chennai |
Korattur |
PPA is for the proposed construction of Basement Floor pt + Stilt + 8 Floors + 9th Floor pt Residential blg with 50 D.Units with Gym. |
1702.85 |
|
|
|
|
|
|
|
78 |
7157 |
03/12/2012 |
C3/17247/2011 |
M/S. VICONS INFRASTRUCTRUE ENVIRONMENTS ENGINEERING PVT LTD NO.16/17 3rd Floor 3rd Cross Street, R.A.Puram Chennai -28. |
Old Door No.19, New No.55, Dr. Muthulakshmi Salai, (L.B.Road) Adayar, Chennai in T.S.No.11, Block No.21, of Urur Village, Chennai. |
Urur |
PPA is for the proposed construction of Double Basement Floor (Mechanized parking) + Ground Floor part + Stilt Floor Part + 17 Floors + 18th Floor part Residential Building with 112 Dwelling Units with Swimming Pool at First Floor Level and commercial space at Ground Floor and incidental use at 1st, 2nd, 3rd and 18th Floor |
8903.18 |
|
|
|
|
|
|
|
79 |
7158 |
03/12/2012 |
C3/9267/2011 |
J. PRAKASH M/S. T.C.G.SOFTWARE PARK PVT LTD No.110, Mount Poonamallee High Road, Porur, Chennai - 600 116. |
S.No.25/4A2, 4D2, 4E2, 4G2, 4H1, 4H2, 4H3B, 4H4, 4H6A, 26, 27, 28/2 of Porur Village, Mount Poonamallee Road, Porur, Chennai |
Porur |
PPA is for the Renewal of Planning Permission the additional construction 4th to 6th Floor over the approved Ground Floor + 3 Floors in Block 1 (IT Building) additional construction of 2nd to 4th over the approved Basement Floor + Ground Floor + 1st Floor car parking Block and Proposed construction of Ground Floor + 8 Floor Block 2(IT Building) and Proposed construction of Basement Floor + Stilt + 5 Floors car parking |
- |
|
|
|
|
|
|
|
80 |
7159 |
05/12/2012 |
C3/7624/2011 |
M/S. AMBATTUR REALITY PVT LTD (GPA) REP BY ITS DIRECTOR SUNIL U.LULLA No.86/E-6, Ambattur Industrial Estate, Ambattur, Chennai -58. |
S.No.36/15 of Perungudi Village |
Perungudi |
PPA is for the proposed construction of Combined Stilt Floor for Block -1 and Club House, Block 3 to 5 and Block 2, Block 1 to 5 Stilt Floor + 9 Floors Residential Building with 186 Dwelling Units and Block 6 Stilt Floor + 3 Floor Club House with Swimming pool. |
13822.4 |
|
|
|
|
|
|
|
81 |
7160 |
06/12/2012 |
C3/14257/2011 |
M/S. AMAR PRAKASH DEVELOPERS PVT LTD No.42, R.P. Road, Chrompet, Chennai - 44. |
S.No.124/2, 228/2, 229/3, 230, 231/1, 2 232/1D, 2, 233/1B, 2B, 241, 242/1A, 243/1, 2A, 2B, 244, 248/2A2, 2A3A of Thirumudivakkam Village at Thirumudivakkam Main Road, Chennai |
Thirumudivakkam |
PPA is for the proposed constructin of Combined Basement Floor for Block 1 to 13, Clube House 1 and 2, Ground Floor + 6 Floors, Block 1 to 13 inter connected at 3rd to 5th Floor level between Block 1 & 2, 2 & 3, 3 & 4, 5 & 6, 6 & 7, Departmental Store in Ground Floor part of Block 7 and Restaurant in Ground Floor part of Block 13, Stilt + 7 Floors (Block 14) for LIG Residential Building with 1312 Dwelling Units and Ground Floor + 3 Floors - Club House 1 & 2 (Gym, Restaurat, Multipurpose Hall and Swimming Pool. |
61035.43 |
|
|
|
|
|
|
|
82 |
7161 |
07/12/2012 |
C3/15217/2010 |
M/S. ASVINI FOUNDATIONS PVT LTD REP BY MS. ARTHY RAZCE (GPA) No.46, Mount Poonamalle High Road, Nandambakkam, Chennai -89. |
T.S.No.1, 2, 3 9/1 & 9/9 Block No.83, Ward - I, Old S.Nos.626, 627part, 628pt, 629/1, 3pt, 1Bpt, 3B1, 4, 5B & 6B of Paruthipattu Village, Avadi, Chennai. |
Paruthipattu |
PPA is for the proposed construction of 3 Blocks ( A, B, C) with Combined Basement, Block A & C: Stilt + 12 Floors + 13th floor pt, Block B : Stilt + 10Floor + 11th Floor pt Residential Buildings with 454 Dwelling Units and Gym |
17158.11 |
|
|
|
|
|
|
|
83 |
7162 |
13/12/2012 |
C3/11630/2011 |
M/S. PRINCE FOUNDATIONS LTD. New Door No.61, Ormes Road, Kilpauk, Chennai - 10. |
R.S.No.799, 800/1, 3, 5 & 803/2, Block No.37 of Egmore Village, Door No.100, 101 & 102 Poonamallee High Road, Chennai. |
Egmore |
PPA is for the proposed construction of Common Triple Basement Floor Common Stilt Floo + 1st Floor + 2 Towers with 2nd Floor to 17th Floor each for Residential purpose 101 Dwelling Units |
7170 |
|
|
|
|
|
|
|
84 |
7163 |
14/12/2012 |
C3/14622/2010 |
V.SUDHAKAR & OTHERS New No.47, 49 Old Door NO.23, 24 Bazullah Road, T.Nagar, Chennai-17. |
New No.47, 49 Old Door NO.23, 24 Bazullah Road, T.Nagar, Chennai-17. T.S.No.5105, 5106 & 5107 Block No.118 T.Nagar Village, Mambalam _ Guindy Taluk, Chennai. |
T.Nagar |
PPA for the proposed construction of Basement Floor + Stilt Floor + 1st Floor (parking) + 2 nd Floor to 10 Floor for IT purpose. |
2071.35 |
|
|
|
|
|
|
|
85 |
7164 |
18/12/2012 |
C3/12235/2011 |
M/S. LOTTEE INDIA CORPORATION LTD Post Box No.720, Murugesan Complex, 2nd Floor New No.84 Greams Road, Thousand Light, Chennai -6. |
Old Mahabalipuram Road, (Rajv Gandhi Salai) in S.No.226/18 of Perungudi Village, Chennai. |
Perungudi |
PPA is for the proposed construction of Basement Floor(parking) + Ground + 6 Floors Office Building. |
1900.37 |
|
|
|
|
|
|
|
86 |
7165 |
18/12/2012 |
C3/4858/2012 |
M/S. A.R.REAL ESTATE DEVELOPERS PVT LTD REP BY ITS MD.THIRU.P.AMARNATH REDDY ACROPOLIS Building Ground Floor, No.148, Dr, Radhakrishnan Road, Mylapore, Chennai -4. |
Door No.5/1165, OMR(Rajiv Gandhi Salai) in S.No.133/1A3A of Palavakkam Village. |
Palavakkam |
PPA is for the proposed construction of Stilt Floor pt + Ground Floor pt + 17 Floors Residential Building (38 Dwelling Units) with Association Hall in Ground Floor and Swimming Pool in Terrace Floor in a single Block. |
3557.32 |
|
|
|
Multi-storeyed Building comprising Stilt Floor(Part) + Ground Floor (Part) + 17 Floors Residential Building with 38 Dwelling Units; Association Hall in the Ground Floor and Swimming Pool in Terrace Floor in a Single Block. |
EC/S-II/4257/2015 |
EC/South-II/279/2015 dated 23-06 |
|
87 |
7166 |
20/12/2012 |
C3/2116/2012 |
M/S. ARIHANT FOUNDATIONS & HOUSING LTD No.271, Poonamallee High Road, Kilpauk, Chennai -10. |
Old S.No.370/1, 370/2, T.S.No.1/11, Block No.60 of Mugapair Village, Church Road, Mugapair East, Chennai |
Mugapair |
PPA is for the proposed construction Stilt + 7 Floors Residential Building with 140 Dwelling Units |
8079.16 |
|
|
|
|
|
|
|